July 2024
- Commons Union
- Furniture delivery began July 7th and will continue through early August.
- External windows have been installed along Commons Lawn (facing east)
- Interior finishes (e.g., stairways, ceilings, carpeting, and doors) are being finalized.
- Outdoor Athletics
- At the football building, HVAC, plumbing, and electrical installations are nearly complete. Final external facia and trim will be installed in mid-July. External site work around the building has begun, including concrete and asphalt paths.
- Final Geothermal field tie-ins are now complete and the large air handler for the building was delivered and installed in early July.
- At the soccer stadium, steel stringers that serve as the base for bleacher seating have been installed. Concrete flooring for the press box and hospitality space was recently poured. Final bleacher and seat installation will begin in late August.
- The stadium’s scoreboard will be installed before the facility’s opening.
- A “first look” at the new facility for Calvin student athletes and coaches is scheduled for August as fall athletics kicks off. A formal dedication ceremony is being planned for October 5th (more details to come!).
- Cadaver Lab
- The Cadaver Lab is complete except for a dishwasher for instrument sterilization being installed in late July. The Virtual Lab will be done in late July.
- A dedication for these new facilities will be planned for September.
Video message
Stories like this get us excited about the future of health education here at Calvin. Watch and learn more about the new Cadaver Lab and Virtual Lab preparing to welcome students this fall semester!
Construction Photo Gallery
Browse, download, or share favorite photos from outdoor athletics, School of Health, and the Hekman Library renovation.
Frequently asked questions
Do you have questions related to construction at Calvin? Email us at: BuildUp@calvin.edu